Objective
Power substation DC system
consists of battery charger and battery. This is to verify the condition of
battery and battery charger and commissioning of them.
Test Instruments Required
Following instruments will be
used for testing:
Multimeter. (Learn how to use it)
Battery loading unit (Torkel-720
(Programma Make) or equivalent.
The Torkel-720is capable of
providing a constant current load to the battery under test.
Commissioning
Test Procedure
1.Battery
Charger
- Visual Inspection: The battery charger cleanliness to be verified. Proper cable termination of incoming AC cable and the outgoing DC cable and the cable connection between battery and charger to be ensured. A stable incoming AC supply to the battery charger is also to be ensured.
- Voltage levels in the Float charge mode and the Boost charge mode to be set
- according to specifications using potentiometer provided.
- Battery low voltage, Mains ‘Off”, charger ‘Off’ etc., conditions are simulated and
- checked for proper alarm / indication. Thus functional correctness of the battery charger is ensued.
- Charger put in Commissioning mode for duration specified only one time during initial commissioning of the batteries. (By means of enabling switch.)
- Battery charger put in fast charging boost mode and battery set boost charged for the duration specified by the battery manufacturer.
- After the boost charging duration, the battery charger is to be put in float charging (trickle charge) mode for continuous operation.
- Some chargers automatically switch to float charge mode after the charging current reduces below a certain value.
- Voltage and current values are recorded during the boost charging and float charging mode.
This test
establishes the correct operation of the battery charger within the specified
voltage and current levels in various operational modes.
2.
Battery Unit
.
Visual Inspection: Cleanliness of battery is checked and the electrolyte level checked as specified on the individual cells. The tightness of cell connections on individual terminals should be ensured.
Visual Inspection: Cleanliness of battery is checked and the electrolyte level checked as specified on the individual cells. The tightness of cell connections on individual terminals should be ensured.
Loading of the battery to be started at the specified current value.
It is to be ensured that all the cell voltages are above the end-cell voltage specified by the manufacturer.